Gas Liquids Engineering (GLE) is providing detailed engineering EPCM services for Enhance Energy’s Origins CCS Hub project, located approximately 5 to 10 kilometres south of Clive in central Alberta. The project will transport dense-phase carbon dioxide from an existing Alberta Carbon Trunk Line (ACTL) riser at Enhance’s Clive Enhanced Oil Recovery facility to a new CO2 injection well at the Origins Hub, where CO2 will be permanently sequestered within the Origins saline aquifer. The initial pipeline will serve the first injection well and support the future development of additional injection wells within the Origins Carbon Hub. The design provides for a transportation capacity of approximately 1.5 million tonnes of CO2 per year

GLE’s scope includes development of the project schedule and Design Basis Memorandum, a Class 3 cost estimate and Basis of Estimate, regulatory and survey support, a pipeline class-location study, wall thickness calculations, bend-list development, equipment sizing, and Issued for construction engineering drawings.

Deliverables include process flow diagrams, piping and instrumentation diagrams, plot plans, pipeline construction typicals, a shutdown key, and a control narrative.

The project includes the following key systems, facilities and engineering features:

  • CO2 Pipeline: An NPS 12 dense-phase CO2 pipeline designed to transport approximately 1.6 million tonnes per year from the ACTL system to the Origins Carbon Hub injection well
  • Pipeline Design Conditions: Operating pressures ranging from approximately 12 000 to 13,400 kPag, with a pipeline maximum operating pressure of 14,890 kPag
  • Pipeline Materials: CSA Z245.1 Grade 359 carbon-steel line pipe with a nominal wall thickness of 12.7 mm, external YJ2K coating or equivalent, and ANSI Class 900 above-ground flanges, valves and fittings
  • ACTL Riser Facilities: New pipeline connection and riser facilities incorporating custody-transfer metering, water-content monitoring and emergency shutdown isolation
  • Injection-Well Facilities: Above-ground piping and equipment including flow measurement, flow control, emergency shutdown isolation and a remote telemetry unit
  • Controls and Communications: Integration of pipeline and metering data into Enhance Energy’s existing SCADA system, with telecommunications requirements to be confirmed through a detailed path study
  • Pipeline Integrity: Provisions for maintenance pigging and future inline inspection, baseline inspection before CO2 commissioning, hydrostatic testing, leak detection, corrosion mitigation and impressed-current cathodic protection
  • Safety and Environmental Design: CO2 dispersion modelling, emergency-planning-zone development, continuous pressure monitoring, low-pressure shutdown protection, and regulatory design in accordance with Alberta Energy Regulator requirements and CSA Z662

"Decades of Expertise Driving Innovative Engineering Solutions"

Building Smarter Energy Infrastructure

To engineer reliable, forward-thinking energy solutions with safety, sustainability, and client value at the core of everything we do.